Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od styblow »

Jojo listopad 2013 se bude jezdit jen na 2 vrstvach, nebudou sjezdy a ani polnacky, na ty bude termin az v roce 2014, finale kolem srpna. :-) Bude to fuska. Od utery skrejvame za mostem ve Vaclavicich a ve stare piskovne se bude zakladat nasep.
balance
Příspěvky: 2183
Registrován: 24.9.2009 10:51:36

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od balance »

balance píše:Ještě by mě zajímalo, pokud PL strana v červnu dokončí most přes Nisu, tak jestli se zprovozní před prázdninama alespoň toto:
http://www.mapy.cz/s/7ajP
Takže odpověď na můj dotaz ... zdá se, že zprovozní.
viz http://forum.ceskedalnice.cz/viewtopic.php?f=197&t=3999
balance
Příspěvky: 2183
Registrován: 24.9.2009 10:51:36

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od balance »

A ještě jeden o něco srozumitelnější článek včetně aktuálního fota mostu přes Nisu. :jidlo:
http://www.hradek.eu/page.aspx?zaz=440-11018
textil
Příspěvky: 14
Registrován: 26.8.2012 8:29:07

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od textil »

Upřesnění otvírání mostu a konce silnice I/35 u Oldřichova na hranicích:
http://www.tvrtm.cz/hranicni-most-mezi- ... 14738.html
balance
Příspěvky: 2183
Registrován: 24.9.2009 10:51:36

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od balance »

Tak most před Nisu otevřen, stejně jako nový kousek I/35 směrem k hranicím ...MAPA a I/35 se napojila na B178n směr A4

Článek: http://forum.ceskedalnice.cz/viewtopic.php?f=197&t=4035

Takže tudy se jezdí už oficiálně ... (staré video z 09/2012)


Má někdo informace jak postupují práce na B178 kolem Herrnhutu?
textil
Příspěvky: 14
Registrován: 26.8.2012 8:29:07

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od textil »

B178 kolem Herrnhutu má být otevřena v listopadu 2013.A zatím to vypadá ,že termín dodrží.
_jan91
Příspěvky: 974
Registrován: 4.9.2011 16:14:35
Bydliště: D1

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od _jan91 »

Ach jo...proč všude se.ou ty kruháče - to patří do města a ne na tranzitní tah silnice I. třídy!
vaclav
Příspěvky: 1831
Registrován: 7.4.2010 11:29:27

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od vaclav »

DefiantM píše:Ach jo...proč všude se.ou ty kruháče - to patří do města a ne na tranzitní tah silnice I. třídy!
protoze je to lacinejsi nez most? byste mel videt francii nebo anglii.
_jan91
Příspěvky: 974
Registrován: 4.9.2011 16:14:35
Bydliště: D1

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od _jan91 »

Stačila by bohatě průsečná úrovňová křižovatka s pruhy pro levé odbočení (což je v podstatě na S11,5 standard). Mluvím teď hlavně o úseku kolem Hrádku na české straně.
Lenny
Autor
Příspěvky: 10799
Registrován: 15.3.2009 22:03:53
Bydliště: na levém břehu Dunaje

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od Lenny »

Otevřeli to 1. 6. či 3. 6.?
D47 už máme, teď ještě D48
Kam teče beton, tam tečou peníze. (Tonda Blaník)
textil
Příspěvky: 14
Registrován: 26.8.2012 8:29:07

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od textil »

Most otevřeli Poláci 1.6.2013 a silnici silnici u Oldřichova n H. 3.6.2013 viz odkaz:
http://www.tvrtm.cz/hranicni-most-mezi- ... 14779.html
Lenny
Autor
Příspěvky: 10799
Registrován: 15.3.2009 22:03:53
Bydliště: na levém břehu Dunaje

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od Lenny »

Řidiči nákladních vozidel se těší na zprovoznění stavby Bílý Kostel - Hrádek n. N. Vratky u Grabštejna jsou pro ně velice problematické, pokud jede vozidlo do protisměru musí zastavit a počkat až projede, jinak se tam nevejde. A taky nadávali na 3 kruháče blízko sebe.
Jak to vypadá s německými úseky, kdy budou další zprovozněny?
D47 už máme, teď ještě D48
Kam teče beton, tam tečou peníze. (Tonda Blaník)
mapman
Autor
Příspěvky: 5763
Registrován: 25.2.2009 22:20:05

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od mapman »

Citace z mezinárodního fóra:
MichiH píše:The future B178 will connect the German A4 Dresden - Görlitz with the Czech R35 (Liberec).

The first section begins at the A4 east of the current AS Weißenberg. Section 1.1 has a length of 5.1km and will get 2x2 lanes (OSM). The plan approval procedure has started in 2010. The order is estimated to be passed in 2013, but complaints are most likely. The groundbreaking ceremony could at best be possible in 2015. The section will feature 2x2 lanes without hard shoulders.

The 6.4km long section 1.2 from road S112 near Nostitz to AS Löbau-West (B6) was opened in 2008 (OSM). The 6.4km long section 2 (Löbau bypass) is in service since 2001 (OSM). Both sections have 2x2 lanes without hard shoulders. The next 5.9km long section 3.1 from AS Löbau-South (S148) to AS Obercunnersdorf (S143) was built from May 2008 to November 2010 (OSM). It features 3 lanes (2+1).

The construction of section 3.2 started directly subsequent to section 3.1 completion (OSM). It is announced to be finished in late 2013, probably in October 2013. This 3-laned section has a length of 10.2km and ends at AS Niederoderwitz (S128).

The plan approval procedure for section 3.3 started long ago. There were many objects, and the plans must be modified. There was no chance to get a final and conclusive plan approval order. A new route near the mountain/hill Pferdeberg must be aligned now. The section has a length of about 5.9km and will feature 3 lanes (OSM).

The 3-laned Zittau bypass is section 4 (OSM). It has a length of 3.6km and was opened in year 2000.

Section 5 is completed and got in service together with the Polish section (OSM). The construction of the Neiße viaduct has been finished in May 2013.

...

Official project page: > click <.
hovi
Příspěvky: 1185
Registrován: 19.11.2010 10:41:31
Bydliště: Liberec

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od hovi »

na konci videoreportáže (čas 1:33) pár záběrů stavby za Václavickou přehradou...
http://www.ceskatelevize.cz/ct24/region ... a-zelenou/
hovi
Příspěvky: 1185
Registrován: 19.11.2010 10:41:31
Bydliště: Liberec

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od hovi »

Mám jen popis výstavby, když jsem projížděl v úterý autem kolem Hrádku. Dostavba je značně rozpracovaná, jsou vidět již jednotlivé vrstvy podloží. Nejsem odborník, ale asi chybí už jen betonová vrstva a pak "asfalt" a obrus + samozřejmě dodělávky. No uvidíme, jestli to do konce listopadu stihnou...
vytrezvitel
Příspěvky: 9
Registrován: 16.5.2012 23:15:36

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od vytrezvitel »

hovi, rozhodujicí bude most na křížení s cestou z Grabštejna do Pískovny. Předminulý týden stavěli konstrukci pro bednění.
hovi
Příspěvky: 1185
Registrován: 19.11.2010 10:41:31
Bydliště: Liberec

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od hovi »

vytrezvitel píše:hovi, rozhodujicí bude most na křížení s cestou z Grabštejna do Pískovny. Předminulý týden stavěli konstrukci pro bednění.
tam jsem nedohlédl... :o)
Lenny
Autor
Příspěvky: 10799
Registrován: 15.3.2009 22:03:53
Bydliště: na levém břehu Dunaje

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od Lenny »

on není vidět ze silnice
D47 už máme, teď ještě D48
Kam teče beton, tam tečou peníze. (Tonda Blaník)
balance
Příspěvky: 2183
Registrován: 24.9.2009 10:51:36

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od balance »

Tak jsem to v rychlosti proběhl od Hrádku směrem k Liberci. IMHO mi nepřipadá úplně reálné to do konce roku (ikdyž provizorně) spustit ... leda by 2 měsíce svítilo sluníčko ;)

http://gallery.ceskedalnice.cz/index.ph ... 27-09-2013
(pouze tento úsek: http://www.mapy.cz/s/8zE9; foceno od Hrádku směr LB)

A videoprůjezd od Hrádku přes PL a obchvat Zittau až na starou B178
http://www.mapy.cz/s/8zG0

kyk
Příspěvky: 957
Registrován: 22.7.2011 10:54:46
Bydliště: Praha, SOKP km 50 st.
Kontaktovat uživatele:

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od kyk »

vidím to na duben, květen; rok už radši nehádám.
textil
Příspěvky: 14
Registrován: 26.8.2012 8:29:07

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od textil »

Odkaz na reportáž ČT: http://www.ceskatelevize.cz/porady/1011 ... regionech/
Kde se vyjadřují k termínu stavby.Jinak před týdnem jsem prošel celou stavbu a je to zoufalství.Budem rádi co zde stále jezdíme když to bude hotové do května nebo června 2014.
bumbik
Příspěvky: 7955
Registrován: 15.12.2010 11:58:09
Bydliště: poblíž III/4806 a D48

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od bumbik »

Dálnice na papíře už máme, ještě je postavit ...
hovi
Příspěvky: 1185
Registrován: 19.11.2010 10:41:31
Bydliště: Liberec

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od hovi »

bumbik píše:tady je přímý link
http://www.ceskatelevize.cz/ct24/region ... edna-zima/
No jo, už u výstavby nové silnice I13 směr Frýdlant byly problémy s přeložkou VVN od ČEZu a zprovoznění se zpozidlo o x měsíců. Způsobuje to tedy ČEZ či neschopnost pracovníků ŘSD, obrázek si udělejme sami...
Dr.Fe1
Příspěvky: 1886
Registrován: 6.8.2010 22:09:08

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od Dr.Fe1 »

Čezáci jsou sice asi taky lotři, ale jak koukám na ty fotky, tak za tuhle nedostatečnou rozestavěnost zjevně nemůžou.
hovi
Příspěvky: 1185
Registrován: 19.11.2010 10:41:31
Bydliště: Liberec

Re: I/35 Bílý Kostel n. N. - Hrádek n. N. - státní hranice

Příspěvek od hovi »

A je to tady, co všichni víme, oficiálně oznámeno na letáku stavby:

"Stavba byla zahájena v květnu roku 2009. Dokončení většiny objektů včetně zbývajících
přeložek vysokého napětí na konci úseku je plánováno do konce roku 2013.
Hlavní trasa a několik drobných stavebních objektů tak bude dokončeno v první polovině
roku 2014. Termín možného zprůjezdnění je 30. 6. 2014 a kompletní dokončení
stavby 31. 8. 2014."

http://www.rsd.cz/rsd/rsdcat.nsf/0/326E ... hradek.pdf
Odpovědět