tady problémy
v 07/2018 se zahájilo prodloužení okruhu Bělehradu, Ostružnice - Bubanj Potok (19.5 km), dokončit se má v 2021
stav na A2, Obrenovac
V 03/2019 se má zahájit výstavba 31 km úseku Preljina - Pozega, což je součást Koridoru XI, postaví to CCCC za 450 mil. €
dále, zde je aktualizace termínu zprovoznění dálnic:
- A1
Section Grdelica - Caričina Dolina, L= 11,8 km
LOT 1 - Roadway and bridges Gornje Polje - Predejane tunnel.
The anticipated deadline for completion of works is 31 December, 2018.
LOT 2 - Roadway and bridges Predejane tunnel - Caričina Dolina.
The anticipated deadline for completion of works is 30 September 2018.
LOT 3 EM - Electromechanical equipment of Predejane tunnel.
The anticipated deadline for completion of works is December 2018.
Section Caričina Dolina - Vladičin Han, L= 14,3 km
LOT 4 - Manajle tunnel.
The anticipated deadline for completion of works is 30 September, 2018.
LOT 4 EM – Electromechanical equipment of Manajle tunnel.
The anticipated deadline for completion of works is December 2018.
Section Donji Neradovac - Levosoje, L= 16 km
LOT 1 - Srpska Kuća - Levosoje, L= 8 km,
The deadline for completion of works is 06/12/2018.
A4
Section Prosek - Crvena Reka L=22,5 km
LOT 2 - Roadway and bridges: Bancarevo tunnel - Crvena Reka
The anticipated deadline for completion of works is December 2018.
LOT 3 EM – Electromechanical equipment of Bancarevo tunnel.
The anticipated deadline for completion of works is December 2018.
Section Staničenje - Pirot east L= 16,64 km
First two sub-sections in the length of 12,3 km have been opened to traffic in a full profile.
The construction of the remaining 4,35 km is in progress.
The anticipated deadline for completion of works is November 2018.